BOND EXTENSION

 

Drawing of front of the Middle School  Link arrow 

Reeths-Puffer Middle School Floor Plan  Link arrow

Reeths-Puffer Middle School Office Floor Plan  Link arrow

Reeths-Puffer Middle School Locker Commons Area  Link arrow

Central Elementary Parking Lot Plan  Link arrow

McMillan Elementary Parking Lot Plan  Link arrow

 

Bond Update

March 9, 2010

 

Bonds Sold and Funds Received

  • $15,000,000 Qualified School Construction Bonds
  • $6,980,000 Build America Bonds
  • Qualified School Construction Bonds - %2.25%
  • Build America Bonds - 4.757%
  • Qualified Bonds limited to $15,000,000

Site work Projects

  • Bids to be received March 15, 2010
  • Running track project to start May 18, 2010
  • Parking lots to begin immediately after school is out for summer

Twin Lake Elementary

  • The library will be moved to the gym immediately after school closes for summer.  Entry and parking will be on the East side of the building.
  • R-P Club Daycare, formerly Little Rockets, will be offered at Reeths-Puffer Elementary for the summer of 2010.
  • Most of the building will be "off limits" soon after school closes for summer. 
  • The new office should be open a few weeks prior to school reopening for the 2010-2011 school year.
  • Bids for the Twin Lake project will be taken at the end of March.

Middle School

  • Major cleaning and removal of unusable items will occur during Spring Break.
  • Electrical power and data connections will be interrupted immediately after students leave for the summer.
  • Office staff will be relocated to the Educational Services Building, 991 W. Giles Road, during the summer of 2010.
  • Bids for building construction project will be taken at the end of March.  Plans and specifications will be out for this work shortly.
  • Some construction will occur when school opens for the 2010-2011 school year.  Construction areas will be sealed off during this period to isolate students and staff from these areas as required by the State Fire Marshall.

 

Bond Update

January 15, 2010

 

Construction Design Stage

The architects, construction managers, technology consultants and school representatives are meeting every other week to review the status of various projects.  At this time, it appears two summers will be required for the work.  Our goal is to have all major work completed by the opening of school in the fall of 2011.  Specific project information will be provided as it becomes available.
 

Parking Lot Repairs and Upgrades

Several locations will have their driveways and parking lots upgraded during the summer of 2010.  The exact locations to be included are currently being determined.

 

Middle School

  • In December, the steering committee visited three middle schools in Grand Rapids to observe and record options.
  • Natural day lighting, safety and security, and a comfortable and welcoming environment were selected as primary factors to be considered as the design process progresses.
  • After students arrive, the design will have visitors entering the main office prior to going into the rest of the building.
  • Additional technology in the classrooms versus in labs is being carefully researched and evaluated.
  • Construction will occur in both the summers of 2010 and 2011. Exact sequencing will be determined over the next couple of months. Office location space will be changed first to open space for other work.
  • Bus and parent student drop-off and pick-up options are being reviewed for efficiency and safety.
  • The students will enter the middle school in a new entry with four doors close to the current main entrance.

McMillan Elementary

Parking lots and building changes are being designed for work to be done during the summer of 2010.

 

Twin Lake Elementary

  • This project is being scheduled for the first summer as we have experienced failures in the heating system which needs replacement as soon as possible.
  • Other aspects of the Twin Lake project should be completed during the summer of 2010.

High School Running Track

  • Soil testing has indicated that the sub-surface materials under the asphalt has become almost like cement in nature; therefore, proper drainage is not occurring and we are seeing major cracks in the actual running surface.
  • Proper sub-surface material will need to be installed prior to the resurfacing of the track. This was budgeted for in the initial bond request.

       

2009 Bond Implementation Schedule  Link arrow
  


Proposal I: Elementary students

Elementary Facilities

  

Goal:  Renovate and upgrade existing school facilities.

 

Cost:  Approximately $6.4 million.  Includes Central Elementary, Twin Lake Elementary, Reeths-Puffer Elementary and McMillan Elementary.

 

Projects: 

Central Elementary - Partial roof replacement, door and hardware upgrades, flooring removal and replacement where necessary and mechanical/electrical upgrades.  Also included are computers, projectors, processors, DVD/VCR's, document cameras, sound enhancement, equipment carts and printers.  Site work includes resurface asphalt paving, asphalt play area, playground drainage, mulch play surface areas.

 

McMillan Elementary - Remove and replace exterior brick, partial roof replacement, door and hardware upgrades, flooring removal and replacement where necessary and mechanical/electrical upgrades.  Also includes computers, projectors, processors, DVD/VCR's, document cameras, sound enhancement, equipment carts and printers.  Site work includes expand/replace asphalt paving, playground drainage, and mulch for play surface area.

 

Reeths-Puffer Elementary - Remodel barrier free toilets, classroom upgrades, sink and toilet replacement.  Also includes computers, projectors, processors, DVD/VCR's, document cameras, sound enhancement, equipment carts, and printers.  Site work includes expand/replace parking and provide signage.

 

Twin Lake Elementary - Replace doors and hardware, remodel offices, toilets, cabinets, mechanical systems and removal and replacement of roofing.  Also includes computers, projectors, processors, DVD/VCR's, document cameras, sound enhancements, equipment carts, and printers.  Site work includes reconfiguring parking and drives, asphalt play surface, and playground improvements including drainage.

 


    Robot Club Members

Reeths-Puffer Intermediate

  

Goal:  Renovate and upgrade existing school facilities.

 

Cost:  Approximately $1.5 million

 

Projects:  Construct new entrance canopies, masonry improvements, door and hardware replacements, remodel school office, remodel barrier free toilets, science room and vestibule remodeling.  Flooring remodel and replacement where needed.  Air conditioning upgrades.  This would include computers, processors, DVD/VCR's, document cameras, sound enhancement, equipment carts and printers.  Site work would include expand and replace parking areas and a new entry sign.

 


    Middle School Students

Middle School

  

Goal:  Renovate and upgrade existing school facilities.

 

Cost:  Approximately $10 million

 

Projects:  Construct new main entrance canopy and lobby expansion.  Building additions, new cabinetry, doors and hardware, folding partitions, ceilings and lighting, fire protection wall and suppression system, replace fire alarm, technology infrastructure upgrades, courtyard infill, and mechanical and electrical upgrades.  This also includes computers, projectors, processors, DVD/VCR's, document cameras, sound enhancement, equipment carts and printers.  Site work includes parking lot improvements, play area upgrades and new signage and fencing.

 


     Biology Student

High School 

 

Goal:  Renovate and upgrade existing school facilities.

 

Cost:  Approximately $3.0 million

 

Projects:  Remove and replace exterior doors, remove and replace selected carpet areas, convert steam boilers to hot water.  This also includes computers, projectors, processors, DVD/VCR's, document cameras, sound enhancement, equipment carts and printers.  Site work includes remove and replace running track surface and asphalt.

  


     

Educational Services Building (Administration Building)

 

Goal:  Upgrade school facility.

 

Cost:  $144,000

 

Projects:  Remove and replace windows, wall panels and framing.

     


 Students learn bus safety

Bus Garage

 

Goal:  Purchase new buses

 

Cost:  $570,000

 

Project:  Purchase eight new buses over 6 years without using General Fund money.

 

 

 

     


 

Duck Creek School

 

Goal:  Maintain School Facility

 

Cost:  $15,425

 

Project:  Replace flooring where necessary.

 


       

Bond Extension Tax Levy Table  Link arrow

 

Table 16a:  Detail for Tax Levy Table (Stauder, Barch & Associates, Inc.)  Link arrow

 

Qualified School Construction Bonds (QSCBs)  Link arrow

 

Technology Planning  Link arrow

 

Application to Treasury  Link arrow